AdventHealth Cath Lab Renovations – Tarpon Springs

Complete de-install GE Mavic operating equipment, new ceiling grid system incorporating cleanroom tiles, and upgrade the electrical outlets. We installed a new surface-mounted wall duct for GE to run the new equipment cables and wires and uplift bracing for the sprinkler system. A new space was created to store tools and documentation for the system. Maintained ICRA plan with Edge Guard panels and negative air monitoring. GE then installed new Mavic 2 equipment and all new paint throughout the space. ICRA/AHCA regulated project.

Architect: Chapuls Design Group